This guide defines the compatibility and upgrade policy for the DOCA Platform Framework (DPF). It explains which combinations of DPF Operator, BlueField Bootstream (BFB), and DOCA Services are supported together, how to move between releases safely, and what DPF guarantees across an upgrade.

DPF ships four General Availability (GA) releases per year and aligns with the DOCA release cadence, including the annual Long Term Support (LTS) train. This guide is version independent: it refers to releases by their position in the annual cycle (January, April, July, October) and uses relative notation such as GAn-1 and LTS-1, rather than naming version numbers, so the policy stays valid across cycles. For the version numbers that apply to the release you run, see Platform Support.

Compatibility commitments

DPF upgrades on two independent tracks:

  • the DPF Operator on the host cluster

  • the coupled BFB + DOCA Service bundle on each DPU

Most of this policy follows from that split. The commitments below apply within the boundaries set out in Scope.

What DPF guarantees:

  • Progressive upgrades. You can upgrade the DPF Operator without taking DPUs offline. DPUs are reprovisioned independently, at their own pace, because the Operator supports DPU workers one release behind it.

  • A predictable reprovisioning cadence. BFB LTS users reprovision roughly once a year, BFB GA users roughly once a quarter.

  • Manifest compatibility. Existing DPF manifests stay compatible across releases within the same major API version. Fields are removed only in the first release of a year (usually the January release), after being deprecated no later than half a year or two releases before (usually the preceding July release).

  • A tested service and BFB pairing. Upgrading a BFB and its DOCA Services together to the same train is the fully tested combination, including staying on the HBN (Host-Based Networking) LTS branch with the matching BFB LTS.

  • Per-DPU rollback. Rolling back to the previous BFB and service bundle is supported per DPU.

What DPF does not guarantee:

  • Running a DOCA Service on a BFB version other than the one it was released with.

  • Any BFB and service combination across the annual cycle boundary (an old BFB with new-cycle services).

  • DPF Operator downgrade.

  • Skipping DPF releases during upgrade.

  • Support investigation while a DPU sits in the rollout-only state. You will be asked to finish moving it to a supported combination first.

  • Support on an older patch within a BFB LTS train. You must be on the latest patch of the LTS train.

Scope

  • This policy covers DPF running in DPU mode on BlueField-3 and BlueField-4 devices. BlueField-2 and NIC mode are out of scope.

  • Where no policy is defined for a given combination, that combination is untested and carries no compatibility guarantee.

  • DPF has no LTS release of its own. Throughout this guide, LTS refers exclusively to the BFB and DOCA Service train, not to the DPF Operator.

  • BFB and DOCA Services are treated as a coupled unit. They are always deployed and upgraded together through a DPUDeployment.

Terminology

Term

Description

BFB

BlueField Bootstream, the firmware and OS image installed on a BlueField-3 DPU

BlueFieldSoftware

The BlueField-4 equivalent of a BFB: the OS ISO and firmware bundle installed on a DPU

DOCA Service

A service (such as HBN) deployed onto DPUs by DPF, versioned together with its BFB

DPF Operator

The DPF control plane, running on the host cluster and managing all DPUs

DPU worker

A provisioned DPU node running a BFB and its DOCA Services

GA

General Availability, a quarterly DPF release (January, April, July, October)

GAn / GAn-1

The current GA release (GAn) and the immediately preceding GA release (GAn-1)

LTS

Long Term Support, the annual (October) DOCA and BFB train

LTS-1

The LTS train immediately preceding the current one

n-1

The immediately preceding release in the same release train

Reprovision

Re-flashing a DPU with a BFB and re-deploying its DOCA Services

Throughout this guide, a component "at release N" means the version that shipped with DPF release N. For a DPU worker, that is its BFB train together with the DOCA Services coupled to it. BFB is used as the general term for the DPU image, and everything said about a BFB applies equally to the BlueFieldSoftware used on BlueField-4.

NVIDIA maintains an LTS BFB for three years. That is the lifecycle of the BFB itself, not the DPF compatibility window. DPF supports a given BFB LTS train for about 15 months, from the October release that introduces it to the following October release. See BFB and DOCA Service support window.

Release cadence and versioning

DPF ships four GA releases per year, each aligned with the matching DOCA train. The October release targets the new annual BFB LTS train and begins a fresh yearly cycle.

DPF release

Aligns with

BFB target

Breaking changes

January

DOCA GA (Q1)

New GA BFB train

Allowed (the only such release)

April

DOCA GA (Q2)

New GA BFB train

Not allowed, additive only

July

DOCA GA (Q3)

New GA BFB train

Not allowed, additive only

October

DOCA LTS

New annual BFB LTS train

Not allowed, additive only

Every release except January is additive only. Breaking changes are confined to the January release, for the reasons described in API and behavior stability.

The months name the usual cadence, and an individual release may shift. Where this guide says "January", read "the first release of a year", and where it says "July", read "two releases before it". The position in the cycle is what the policy depends on, not the calendar month.

How DPF is upgraded

DPF has two layers that upgrade independently, on separate schedules:

  • The DPF Operator (the control plane) runs on the host cluster and manages every DPU.

  • Each DPU worker runs a BFB together with its coupled DOCA Services.

Understanding these two tracks is the key to planning any upgrade.

Aspect

DPF Operator

BFB + DOCA Services

Where it runs

Host cluster (control plane)

DPU workers

Upgraded by

In-place Helm upgrade

Reprovisioning the DPU

Upgrade step

One DPF release at a time (n-1)

One BFB train at a time

Typical cadence

Each DPF release you adopt

BFB LTS about yearly, BFB GA about quarterly

Version skew

Runs up to one release ahead of its DPUs

May run one release behind the Operator

Rollback

Not supported

Supported per DPU

Two rules make this model work:

  • The control plane may run ahead of its workers. A DPF Operator at release N stays backward compatible with DPU workers at the previous release (N-1). You upgrade the Operator first, then reprovision DPUs at your own pace.

  • BFB and DOCA Services move together. A DOCA Service version is always deployed alongside the BFB it was released with. Running a DOCA Service on a different BFB is untested.

Upgrading the DPF Operator

Upgrade one release at a time (n-1)

The DPF Operator can be upgraded only one release at a time. Skipping a DPF release is not supported.

Each release may add APIs, migrate fields, or complete a deprecation, and these steps must be applied in order. Each release may also raise the Kubernetes minor version of the DPU cluster control plane. Kubernetes control planes must be upgraded one minor version at a time under the Kubernetes version skew policy, which likewise blocks skipping a DPF release.

You do not have to work this out yourself. Before an upgrade proceeds, the Operator validates the version skew across every DPU cluster, comparing each ready DPU's kubelet against the cluster's API server, and blocks the upgrade if the policy would be violated.

A full annual upgrade path therefore looks like this:

DPF-Oct -> DPF-Jan -> DPF-Apr -> DPF-Jul -> DPF-Oct (next year)

The rule applies to the release, not to its patches. DPF versions are numbered year.month.patch, and patch upgrades within the same release are always allowed, so you can take a fix such as YY.M.0 to YY.M.1 at any time without it counting as a hop.

The n-1 policy applies to the DPF Operator itself, independent of the BFB running on the DPUs. Even when DPUs stay on an older BFB LTS, the DPF Operator must still pass through each release in order.

Mixed-version clusters

During a rolling upgrade the cluster is temporarily in a mixed state, which DPF explicitly supports:

  • A DPF Operator at release N supports DPU workers at release N-1. The control plane can be one release ahead of the DPUs it manages.

  • While a DPU still runs the previous BFB, it operates with the feature set of the previous DPF release. New features that depend on the newer BFB become available on that node only after it is reprovisioned. Each such feature documents its minimum requirement as a (DPF release, BFB train) pair.

Upgrading across multiple releases

To advance more than one DPF release, choose one of two paths.

Option 1: Sequential rolling upgrade (no full cluster downtime). Upgrade one release at a time while keeping most of the cluster operational. Any hop that also moves the DPUs to a new BFB train requires a full DPU rollout and a reboot of every DPU node before the next hop begins. Hops that stay within a supported BFB train, as an LTS user's hops do through a year, need no rollout in between. Availability is preserved throughout, at the cost of one power cycle per rollout.

N -> N+1 (full DPU rollout + reboot) -> N+2 (full DPU rollout + reboot) -> ...

Option 2: Offline upgrade (single power cycle). If full cluster downtime is acceptable, complete several DPF hops with a single DPU rollout at the end.

  1. Take DPUs out of service by removing DPUDeployments, or by narrowing dpuNodeSelector so that it matches no nodes, leaving no workloads scheduled on the DPUs.

  2. Upgrade DPF one release at a time (N to N+1 to N+2 and so on), with no DPU provisioning between steps.

  3. After reaching the final DPF release, perform a single DPU rollout to the matching BFB train and power cycle the DPUs.

  4. Restore DPUDeployments to bring services back online.

DPUs offline -> DPF N -> N+1 -> ... -> N+x -> single DPU rollout + power cycle -> DPUs online

Between steps 2 and 3 the DPUs run a BFB train that the newer DPF releases no longer support, which is an untested state. Taking the DPUs out of service in step 1 is what keeps Option 2 within supported combinations, so the cluster downtime is not optional.

Downgrade is not supported

DPF Operator downgrade is not supported once an upgrade has been applied. An upgrade may advance CRD schemas and migrate stored resources, and reverting those changes safely is not feasible. If you hit an issue after an upgrade, roll forward to the next DPF release rather than attempting a downgrade.

Rolling back the BFB and DOCA Service bundle is a separate matter and is supported per DPU. See Rolling back a DPU.

BFB and DOCA Service support window

Each DPF release fully supports the matching DOCA BFB train, with BFB and services at the same version. Alongside it, the release also supports the immediately preceding GA train and the current BFB LTS train, so DPUs can be rolled forward progressively rather than all at once.

The matrix below follows one full annual cycle. It is version independent. For the concrete versions of the release you run, see the BlueField OS, Firmware and Services Support Matrix.

BFB train

DPF-Oct (prev)

DPF-Jan

DPF-Apr

DPF-Jul

DPF-Oct

BFB LTS-1 + services

✓

✓

✓

✓

✓

BFB GA-Jan + services

-

✓

✓*

-

-

BFB GA-Apr + services

-

-

✓

✓*

-

BFB GA-Jul + services

-

-

-

✓

✓*

BFB LTS + services

-

-

-

-

✓

Legend:

  • ✓supported: fully tested with this DPF release. You can stay on this combination for as long as the train remains in its support window.

  • ✓*rollout only: allowed to operate while you move DPUs forward, tested with the feature set of the previous DPF release. This is a transitional state, not a resting place: reprovision before the next DPF release, and expect to be asked to update first if you open a support case.

  • -unsupported: reprovisioning to a supported combination is required.

How to read the matrix. Each row is one BFB train's support window across the year. A GA train is fully supported in its own quarter and then rollout only for one more release. An LTS train instead stays fully supported for the whole cycle, in parallel with the shorter GA windows, which is what lets you stay on it without reprovisioning. The top row follows a single LTS train, the one introduced at the October release that opens the cycle. It is the current LTS for its year and becomes LTS-1 when the next LTS ships in the last column, which is where its window ends: about 15 months, or five DPF releases, from October to October. Past that point it is unsupported and the DPU must be reprovisioned. What that means for your own schedule is covered in How often you reprovision.

Within a BFB LTS train, only the latest patch release is supported. If you run an older patch of the same LTS train, update to the latest patch before opening a support case.

How often you reprovision

The DPU rollout cadence depends on which BFB train you run:

  • BFB LTS users reprovision once per year, at the October release, when the new BFB LTS becomes available. A BFB LTS is supported across all four DPF releases of its year and the following October release, so no reprovision is required for any hop in between. Applying an LTS patch (for example, a security fix) requires an additional rollout whenever you take it.

  • BFB GA (non-LTS) users reprovision roughly once per quarter. Each BFB GA is supported for only two consecutive DPF releases (one fully supported, then one rollout only). Reprovision to the next BFB train before advancing to the DPF release where your current BFB is no longer supported.

Rolling back a DPU

BFB and DOCA Service rollback is supported per DPU. Because reprovisioning re-flashes the DPU and re-deploys the service containers, rolling back to the previous BFB and service bundle is safe for any combination the matrix above still shows as supported at your DPF release. Rollback is independent of the DPF Operator, which cannot be downgraded.

DOCA Service compatibility

Interoperability during a rolling upgrade

A rolling upgrade briefly runs two versions of the same DOCA Service side by side across DPU nodes, so every DOCA Service deployed by DPF must keep working across that transition. NVIDIA's built-in services already meet this requirement, so it concerns you mainly if you develop or package your own DOCA Service:

  • The current GA version of a service (for example, HBN GAn) interoperates correctly with the previous GA version (HBN GAn-1) across DPU nodes in the same cluster.

  • At a BFB LTS boundary, the current update of the new LTS train interoperates correctly with the latest update of the previous LTS train.

  • Third-party services that run multiple instances across DPUs (for example, load balancer nodes on separate DPUs) are held to the same requirement.

A service that cannot run alongside its previous version across DPU nodes cannot be upgraded without downtime, and is therefore not supported for rolling upgrades.

Service versioning and LTS

DOCA Services do not have LTS releases of their own, and a service version always matches its BFB train. HBN is the exception. HBN maintains a separate LTS branch tested against the matching BFB LTS. Staying on the BFB LTS with the HBN LTS branch is a fully tested combination.

API and behavior stability

You may run several DPF upgrades between DPU rollouts. BFB LTS users move through all four DPF releases of a year without reprovisioning, and an offline upgrade (Option 2) applies several DPF upgrades in a row before a single rollout at the end. Keeping this safe requires DPF APIs to stay backward compatible across releases, so breaking changes are strictly limited in both scope and timing.

Non-breaking versus breaking changes

Non-breaking changes may be made in any DPF release, with no deprecation window:

  • Adding a new optional field.

  • Relaxing validation (widening a constraint, making a required field optional, or adding allowed values).

Breaking changes are permitted only in a January release and follow a two-phase deprecation process. They include:

  • Removing a field or resource.

  • Tightening validation (making an optional field required, or removing allowed values).

  • Renaming or moving a field (treated as removing the old name and adding a new one).

  • Changing a field type in an incompatible way.

The deprecation window

A field or resource is marked deprecated no later than the July release preceding its removal. The deprecation is recorded in the CRD schema, names the release that will remove the field, and the user guides stop referencing it. The field keeps working until it is removed in the named January release, which ships with migration guidance.

Deprecated: no later than DPF-Jul  ->  Still works across DPF-Jul and DPF-Oct  ->  Removed: DPF-Jan

Because deprecation lands by July and removal happens no earlier than the following January, the deprecation window always spans at least two releases.

If you adopt a new BFB LTS at the October release, you may keep the same configuration for a full year. The October release therefore never breaks an existing configuration, and any planned removal is already marked deprecated in the CRD schema before you set that yearly configuration up.

Runtime surfaces used by DOCA Services

During an October upgrade, DPUs and their DOCA Services still run the previous version while the new DPF Operator is already live on the control plane. Removing a DPF behavior that running services depend on would break them mid-upgrade. Any DPF surface that a DOCA Service or chart consumes at runtime, such as config ports, controller-injected annotations, or labels read through the downward API, is therefore changed or removed only in a January release, never at October.

Finding deprecated fields in your manifests

Start with the DPFOperatorConfig. It exposes a status condition that reports deprecated field usage across your applied manifests, so you can see everything that needs migrating before the next January release in one place, without reading release notes.

To inspect a single field, the deprecation notices are also recorded in the CRD schemas, so kubectl explain reports them straight from the cluster:

$ kubectl explain dpudeployment.spec.dpus.dpuSets.dpuSelector
GROUP:      svc.dpu.nvidia.com
KIND:       DPUDeployment
VERSION:    v1alpha1

FIELD: dpuSelector <map[string]string>


DESCRIPTION:
    DPUSelector defines the DPUs that the DPUSet should target

    Deprecated: This field is deprecated and will be removed with vYY.1.0. Use
    DPUDeviceSelector instead.

The notice on a real field names the concrete release that removes it. vYY.1.0 above stands in for that release, because this guide does not name version numbers.

Migrate any field carrying such a notice before you upgrade to the release it names.